During March While doing day begin in Sub accounts module a message appears. Most of the SPMs and Supervisor firstly just ignore the message. The message is about configuring the Last working day of the March and First working day of April. If you ignore the message while day begin of next day this message also reappears.


Solutions:



Log in as ---Supervisor -->
Go to configuration -->
Select Supplementary Dates -->
Current Year  2012
Last working day of March   31-03-2012
First Working day of April    02-04-2012
Save
This will solve the error